Medical procurement

Needs definition

  • clear specifications including shelf life requirements
  • use medicinal names rather than brand names
  • special requirements
  • include sample quantities in total order where necessary.

Shelf life calculations

  • Paracetamol has a 30-month shelf life. Requestor asks for 90 per cent remaining shelf life (27 months) at delivery.
  • Import lead time is four months.
  • International procurement will not comply with requestor’s requirements. Options: lower the minimum remaining shelf life required or procure locally.

Supply chain requirements

  • Restricted items mean stricter import rules and controls.
  • Check transport and storage conditions needs (ex: cold chain).
  • Check who can be a consignee of imported medical supplies.
  • Check requirement for testing or sampling at arrival in country.

National regulations

  • Check national essential medicines list for any limitations or requirements in importations.
  • Some countries require that importers of specific medical suppliers be registered as such.

Procurement agent services

  • Procurement can be delegated to a procurement agent (at a cost).
  • Tendering is required for procurement agent contracting.

Supplier selection

  • Request for support from ICRC/IFRC procurement experts.
  • All procurement of medical items done under IFRC rules must be approved at GVA level.

Read more about medical procurement here.


Consultancy services procurement

In the British Red Cross, this is currently not managed by logisticians, although this is under discussion as it technically is a procurement process – contact international HR for details on the process to recruit consultants.

A process flowchart is available from international HR for more details on consultancy services procurement.


Facilities rental services procurement

The needs definition phase should focus on:

  • area of choice
  • safety and security
  • building/compound size
  • number of bedrooms/offices required
  • amenities
  • space needed for parking vehicles and storage
  • preference for serviced property.

Seek recommendations from peer organisations or rental agencies, with options compared in a CBA format.

The CBA and the recommendation should then be approved by a budget holder, procurement manager and finance manager, with the security focal point included for information.

Negotiations with selected supplier or service provider should ensue.

Negotiation points should confirm:

  • rent amount
  • regularity of payment
  • period of notice to close contract
  • shared maintenance responsibilities
  • responsibility for building and contents insurance
  • responsibility for payment of utilities.

Due diligence must be carried out before the contract is issued to the supplier or service provider.

Rental invoices should be sent directly to the finance team (or SSC in British Red Cross UK) for payment with a copy of the rental contract.


Facilities management in the UK

In the UK, the facilities team at SSC will support the selection and contracting process. The facilities team should receive invoices for all property rentals and process property-related payments directly.

SSC holds a framework agreement covering maintenance and services to property rented by the British Red Cross. Service requests must be placed through SSC’s support desk, who liaise with the facilities management company and allocate a level of urgency to every request.

Requestors of building services will be informed of the timeline for service delivery directly. More information on the facilities team and their support can be found on Redroom.

There is a requirement for the British Red Cross to have specific documents available on British Red Cross-run sites at all times, in a “statutory documents folder”. More information about the statutory documents folder can be found on Redroom.


Selection criteria for rental premises

In general

Two text boxes describe the selection criteria for rental premises. One lists desired qualities including a secure location, at least two exit routes, access to secure parking and access to  a generator. The other lists qualities to avoid such as proximity to a military compound or other risk-prone areas, communication restrictions and liability to flooding

Given the status of PNS in country (working for the IFRC and not having legal authority in country), whenever considering property rentals, make sure the legal authority in country is involved in the process and kept informed at all stages.

The lease agreement must eventually be signed by the legal authority in country.

Warehouse selection

See the Building a stock strategy and Sourcing a warehouse sections of the Warehousing chapter.


Accommodation

As a rule, prioritise secure facilities such as an apartment, house or other fully self-contained area, or containers or prefabricated buildings in a compound. Considerations listed in the In general section apply.


Office space

Where the British Red Cross works in partnerships, it is usually possible to be hosted by either the NS, the IFRC or the ICRC, following the terms of an integration or service agreement (IA). The use of office equipment is usually provided on either a free or cost-sharing basis, or as part of the service/integration agreement.


Sharing premises within the Movement


As a PNS, it is usually not possible to acquire land or property in a country other than the PNS’s own; however, where relevant, a business case should be put together to provide a costs-benefit analysis to compare acquisition and rental options. A PNS willing to rent premises outside their own country would have to go through the HNS or IFRC to rent spaces for them.

If renting space from the IFRC, service charges must be defined as part of the integration agreement or through a separate agreement.

See the Policy and Procedure for Provision of Integration and Administrative Services for National Societies from the IFRC for more details on integration and service agreements.

A text box describes how to conduct due diligence on property leasers. This involves checking ownership documents and the name of the owner and agency marketing the property to ensure there are no links to terrorist acts

If renting space from the HNS, service charges can either be defined in the GAD or agreed locally.

Any examination of a new site should use the NS security audit checklist and ideally be carried out by a security adviser from the IFRC.



Clearing and forwarding services procurement

Read about the procurement of clearing and forwarding services here.


Procurement to support cash programme delivery

For more details and useful resources about cash programming, refer to the British Red Cross Cash Hub.

The Cash Hub platform, hosted by the British Red Cross as a shared leadership initiative with IFRC and ICRC, has been launched as a global resource for the Movement to help increase the Movement’s capacity to deliver cash assistance. All templates referred to in this section are available on the Cash Hub via the search function, mostly from the Cash and logistics section.

Visit the Cash Hub here and join the online cash community of the Movement: the platform offers support to expand our knowledge, skills and networks in different ways, such as searching through a range of resources, training opportunities, programme guidance and tools, or accessing interactive cash maps with key data on cash programmes.

The vast majority of cash programmes will require tendering for financial services and/or voucher services. The requirements for cash services must be defined by the programme team, using the scope of work template and the response sheet as a reference. Note that there are separate response sheet templates to use for FSP procurement and voucher vendors procurement. Using these resources will ensure that you collect the minimum information necessary to ensure the tender is successful.

A text box describes the cash and vouchers assistance programme which is a humanitarian response based on the transfer of cash, or vouchers, to individuals, households and communities

The modalities of cash distributions must be defined in a supply chain strategy and associated services must be captured in a procurement plan, so they can be sourced, contracted and monitored by procurement experts with consultation of finance and programme experts.


Cash services providers must be evaluated jointly by programme, finance and logistics, through a tender process or a simple CBA.

The most common services that cash programmes require are:


Delivery
mechanism
Cash transferCash transfer
ModalitiesIndividual cash assistance
Community grants
Vouchers
OptionsDirect cash distribution
Cash by third party provider
e.g. Bank, post office, mobile phone
company, money transfer service,
Hawala
Value vouchers* - beneficiaries purchase whatever
they need, up to voucher face value
Commodity vouchers - beneficiaries purchase
a specific commodity, price pre-agreed
with traders and retailers

*Although beneficiaries can choose what they want to buy, the choice will still be limited to the products a certain shop offers, and often limited to a pre-determined set of items.

To define the procurement process to follow, refer to the flowcharts in the Quote-based procurement section of Sourcing for procurement, making sure the distinction is made between the value of the vouchers or amount of cash distributed and the cost of delivery.

The ICRC have published a step-by-step guide to cash transfer programmes tendering on the Cash Hub which helps planning for the entire procurement process.

Take the Cash assistance through Financial Services Provider training, a 90-minute online modular training outlining critical steps and tools to successfully contract an FSP. The training is accessible from the Cash Hub here.


Cash procurement rules:


  • Value voucher cash programmes – Only service fees to be charged by the third party or transfer service provider define the authorisation level and procurement process to follow (e.g. services to print vouchers or to encash vouchers), not the face value of the vouchers distributed.
  • Commodities voucher cash programmes – The combined value of the commodities and service fee determine the authorisation level and procurement process to be followed.
  • Cash assistance through Financial Service Provider< 1,000 CHF: single quote procurements is sufficient but regional/central quality check required. Use of the SoW response document is not mandatory but recommended.

    > 1,000 CHF: Run tender (preferably restricted) with support from regional/central logistics team (UKO, IFRC or ICRC).

See the Assessment section on the Cash Hub for guidance on tendering for financial service providers.


The following applies to all services:


  • Where the procurement experts reviewing the process identify a risk, they may escalate its validation to the funding PNS for further review.
  • The selection of a financial services provider should always be validated by a central procurement team (PNS at minimum, funding PNS where value of procurement is greater than £25,000).

Sourcing a financial services provider

Look up existing resources on the Cash Hub, under the assessment section, to find guidance on how to assess service providers and lay out a risk register for a cash response.

The roadmap at the start of the assessment section gives useful general information, and the “financial service providers baseline checklist” and the “mapping service provider template” are also available. There is also an “assessing FS topics and sources template”. All templates are available from the Cash Hub.

Other information sources that can support the selection of an FSP:

  • Logistics, procurement and programmes collect information on the service providers in the market. Finance should be included in the assessment, too – if possible, they should lead, together with programme, as they have the necessary technical knowledge of FSPs.
  • Finance should also be involved in setting the requirements for FSPs, as they will need to be able to transfer the money to them, pay them on time and have the requirements met for reconciliation of funds. They may also hold a list of potential FSPs.
  • Identify and narrow down potential service providers that fulfil your requirements. Sourcing can also be supported by consulting other humanitarian organisations that already implement cash-based responses and have established contracts with service providers.
  • The IFRC FSP Framework Agreement Tip Sheet available from the Cash hub provides an outline of the critical differences if a long term (2-4 year) framework agreement is put in place rather than a standard service contract to ensure the process is completed comprehensively, and in compliance with the IFRC Procurement Manual.

There are strong regulatory controls around financial transfer services including (but not limited to) anti-money laundering (AML); counter-terrorism financing (CTF) and know your customer (KYC) procedures. Due diligence is therefore a key mitigating action against the risk of using an FSP for the delivery of a cash programme and will ensure both compliance and the technical quality of the services delivered.

A pre-qualification step should occur before the tender is published, with a Request For Information (very similar to the EOI) sent to potential suppliers (the supplier registration form can be used as an RFI when accompanied by background information on the future tender). The FSPs who respond should be evaluated against a pre-defined set of criteria. Pre-qualified suppliers should then be invited to tender (see the Tendering for goods and services section of Sourcing for procurement for more details on restricted/open tenders). This is the preferred option, but if there is insufficient time to undertake two steps, an open tender can be the preferred route to select an FSP. Technical and financial proposals must be requested and received from suppliers or FSPs and after the technical evaluation only those eligible will be considered for the financial evaluation.


Standard selection criteria for FSPs

Check the Cash Hub’s Procurement tools and templates section for guidance on the selection of service providers and use the CBA template for Financial Services Providers (FSPs) available in the section resources to define criteria and requirements.

Standard criteria include:

  • Can the FSP pre-finance the cash grants value?
  • Does the FSP charge account fees to users and recipients? If so, cost of account fee must be included in the amount of cash distributed.
  • Payment terms: unless otherwise agreed with the FSP, the payment terms of the procuring PNS will apply. Payment should be processed following thorough reconciliation.

standard contract for FSP has been designed by the ICRC. It will require adapting to the contracting organisation’s specific requirements.

For a voucher programme, retailers need to be contracted as service providers and all usual contracting requirements should be followed. A tip sheet for voucher programmes is available from the Cash Hub. A standard template for voucher printing services is also available from the Cash Hub under the Procurement tools and templates section.

A text box describes the role of the Cash-logs SMCC (Strengthening Movement Collaboration and Cooperation) working group which brings stakeholders together to agree on technical support and responsibilities for cash programming

Regular monitoring of the retailers and voucher providers is important from the procurement side, to ensure they hold the right items (in quantity and quality), offer fair and transparent prices, etc. The information collected from the retailers must then be triangulated with the beneficiary monitoring data to initiate payment of the retailers and of the voucher provider (reconciliation).


When using FSP services to transfer cash to beneficiaries, logistics must be involved in the reconciliation process before payments are processed. Logistics also supports the performance management of the selected FSP(s) throughout the contract implementation phase – see the Managing the performance of contracts and suppliers section of Managing procurement).

The reconciliation process should be formalised with a Certificate of completion and/or a service delivery note, available from the procurement tools on the Cash Hub.


Construction material

Where construction activities aren’t subcontracted, the organisation takes responsibility for conducting the procurement of construction materials.

A supply chain strategy is important for any programme requiring supplies but is crucial for construction projects. An analysis of the supply options needs to be included in the programme design.

Some points to consider when procuring construction items:

Direct delivery to construction sites

  • Direct delivery by supplier is preferred.
  • If supplier enters organisation’s premises, ensure safe access and prevent any image issues due to association (thorough supplier due diligence, precise communication to staff and other visitors).

Quality control

  • Consider hiring external resource to help with QC.
  • Quality of supplies AND quality of service must be controlled.
  • Assess supplier supply chain (ethical due diligence).

Storage of construction materials

  • Consider whether to use own warehouse vs temporary storage vs drip-feed deliveries.
  • Ensure safe storage.
  • Consider storage support options from local community.

Construction timeline

  • Often under one year in duration.
  • Build staggered deliveries into agreement with supplier.

Price fluctuation

  • As much as possible, agree fixed prices for the duration of the works.

Location of construction site(s)

  • Must have access to local markets.
  • Include transport costs in project budget.

Note that all procurement of construction items or services done under IFRC procurement rules MUST be approved by the procurement authority in Geneva before issuing a contract.


Food and seeds

The British Red Cross rarely supports the procurement of food and seeds. National Societies would typically seek advice from the IFRC or ICRC purchasing teams for such procurements, to manage the risks associated with procurement of food and seeds (mostly phytosanitary). For further information, see Section 3.4 of the IFRC’s procurement manual, which is dedicated to the procurement of food and seeds.

In many ways, the standards for procuring food and seeds are similar to those that apply to procurement of medical items: strong controls are in place to ensure goods are fit for consumption, and to protect national production – some countries will not allow food and seeds to be imported for example.

Always refer to your regional logistics coordinator for advice on procuring food or seeds.


Vehicles

See the Fleet chapter for details on the procurement of fleet.


Read the next chapter on Warehousing here.



Download the full section here.

Tracking procurement


Use a procurement tracker to monitor and report on the progress of requests and procurement processes, and to highlight and communicate obstacles and delays. This should be shared with the programme team and requestors at an agreed frequency and should inform monthly project meetings. Where there are significant obstacles to timely procurement, the programme team and requestors must be consulted.

Looking at the procurement tracker, procurement leads should also be able to highlight procurements that need to be initiated in order to meet the requested delivery timeline on the procurement plan.


Supplier database

Maintaining a supplier database per category is useful for multiple reasons:

  • Closed tenders or RFQs can be sent to all registered suppliers.
  • Registration documents and suppliers’ policies can be shared in advance, saving time when necessary.
  • They can be used to the record number of transactions with each supplier, the total amount spent in a year, etc.

In the UK, CPT does not keep a supplier database but they maintain lists of pre-qualified suppliers for specific items who can be called upon for higher-value procurement, so it is good practice to contact them or international logistics to check with one or both when sourcing items.


Managing the performance of contracts and suppliers

Maintain a separate list of ongoing contracts, including their validity dates and total value.

Monitor supplier performance against a contract’s service-level agreement and hold one or two meetings each year to review performance and amend contracts where necessary. The supplier performance matrix can be a good guide for these supplier performance meetings.

Suppliers can be appraised against the terms of the contract: standard indicators to track include “On Time In Full” (OTIF), order turnaround time and delivery claims. When managing long-term contracts, it is recommended to have standard key performance indicators in place, against which performance can be measured over time.

Managing the performance of financial services providers (FSPs) in cash programmes is critical as they play such a key role in the successful implementation. See the Procurement to support cash programme delivery section of Procurement of special items and services for more details.

Contracts in the UK are managed and reviewed by the CPT. They will contact the logistics team when contracts are expiring or a supplier performance meeting is due and the logistics team can give feedback either through the supplier performance matrix and taking part in review meetings or by working with stakeholders to decide on contract extensions or terminations.

Contact the corporate procurement team for more information about the supplier scorecard and supplier management in the UK.


Managing deliveries

The delivery of goods or services against approved POs and contracts must be planned, prepared and documented.

Agreeing deliveries can be done in the contract or PO, through a schedule and agreement of responsibilities.

It is good practice to agree delivery terms against the official list of international commercial terms (incoterms) to ensure all parties understand their responsibilities, particularly in cases where the goods or services are sourced internationally.

The expected receiver of physical goods (the warehouse officer, storekeeper or receptionist) must be informed at least 48 hours in advance of the planned delivery so they can ensure they have got space, resources and time to process the delivery.

To learn more about incoterms, refer to the Specifics of international movement section of Types of Movements: local and international.


Documenting deliveries


Delivery of goods must be accompanied by a delivery note prepared by the supplier and a goods received note (GRN), raised by whoever is processing the delivery internally. The GRN, which will eventually have to be signed by the requestor of the goods, should mention any discrepancy in quantity or in quality against the expected delivery and be signed by the delivering party, the receiver and the requestor.

What is stated in the GRN must match what is reported in the stock records. See the Transport chapter for more details.

The delivery of services must be confirmed with a qualitative appreciation of the services delivered. In the UK, where there is no form to confirm receipt of a service, this is done through the Agresso tick-box process, or with a GRN where the procurement has been conducted outside of Agresso.

A separate document such as a certificate of completion (also called a service delivery note in the IFRC procurement manual) should be used to confirm the quality of the service, but a simple note can be added to the GRN to confirm that the services delivered met the agreed standards. This must be signed off by the requestor of the service and a technical expert. Note that this is the form to use when confirming receipt of cash transfer or voucher distribution services.

Once approved, the GRN and all affiliated documents become part of the procurement file. Where there are discrepancies recorded at delivery, these must be detailed on a claims report, signed by both parties. Partial deliveries must be specified on the GRN, or the certificate of completion if used.


Processing payments

Payments can only be processed by finance staff, based on a fully documented procurement process.

Invoices for delivered services or goods must be addressed to finance (not to the signatory of the GRN/certificate of completion) and matched with the procurement files handed over to the finance focal point. Where a claims form is attached to the procurement file, finance should consult with the receiver to ensure the contents of the claim matches the payment amount. No payment can be issued to suppliers without a completed GRN/certificate of completion.

Invoices for delivered services or goods in the UK must be addressed to APInvoices@redcross.org.uk (not to the signatory of the GRN/certificate of completion) and matched to an Agresso purchase order. The invoices are then posted on Agresso and a notification is sent to the person who raised the purchase order to post a GRN against it to authorise payment. As the requestor is likely to be different from the receiver, the requestor must ensure they have a copy of the receiver’s GRN before authorising it on Agresso and they should attach a copy of the GRN to the procurement file. See the UK Procurement processes flowchart for a summary of the process to follow from requisition to payment.

Where the supplier has failed to deliver on a product or a service, the outcome of this must be agreed before they post the GRN on Agresso. If the supplier accepts liability, they can issue a credit note that must be sent to SSC and posted to Agresso. The requestor can then post a GRN against the purchase order and the credit note at the same time, so when payment is approved it takes off the value of the credit note.

The preferred payment terms of the British Red Cross are 30 days after invoice against delivery and issuing of a clean GRN. Exceptions can be made (see the “advance payments” information below), in particular in cash transfer programmes.

Where the invoice amount differs from the Agresso PO amount by more or less 20 per cent, SSC will ask for the PO amount to be modified and for the PO to be approved again through the Agresso workflow.

Advance payments can be agreed but need to be flagged to finance.

Advance payments must be supported by partial GRN or pre-agreed contractual terms. A partial GRN or certificate of completion can be submitted to SSC for payment against partial invoices, but the original purchase order should be split into lines to match the expected schedule. Where advance payments are required, it is advised – although not always possible – to pay a maximum of 30 per cent of the contract or PO value.


Exceptions apply for pre-financing of cash transfer services with financial services providers (see the Procurement to support cash programme delivery section of Procurement of special items and services.)


Documenting and filing

Procurement files must be completed and handed over to finance for payment and filing.

Copies of original requisitions, POs, contracts and GRNs must be kept by logistics, either by procurement file or by type of document.

The UK procurement process flow diagrams show which documents are mandatory by threshold – always check for donor requirements in terms of retention time and specific documents to include in the procurement file.

FinanceLogisticsSupplier
RequisitionOriginalOriginal
Quotation(s)OriginalCopy
WaiverOriginalCopy
Supplier due diligence reportOriginalCopy
RFQOriginalCopy
RFPOriginalCopy
Tender bidsOriginalCopy
Tender committee TOROriginalCopy
Tender committee meeting minutesOriginalCopy
CBAOriginalCopy
Letter to successful/unsuccessful biddersOriginalCopyOriginal
POOriginalCopyOriginal
ContractOriginalOriginal
GRNOriginalCopy
Contract extension formOriginalOriginalOriginal
Invoice(s)OriginalCopyOriginal
Proud of paymentOriginalCopy

Available to download here.


Procurement files should be kept on archive for various durations, depending on the requirements that apply.

The CPT in the UK retains copies of the tender documents and procurement process as well as documents relating to ongoing frameworks and supplier performance. International logistics can retain a local copy as well, for reference. Copies of original requisitions, POs, contracts and GRNs are kept by logistics in separate files in the British Red Cross international quality methodology filing system (PIMS).

UK (HMRC)Six years
ECHOFive years
BRC GAD standardsInvoice and purchase orders: six years plus current year
Contracts: end of contract plus eight years
Supplier selection documents (tenders, minutes and evaluations): three years

Read the next section on Procurement of special items and services here.



Download the full section here.

Defining the need for goods or services

In the UK

Procuring against UK contracts

View a step-by-step guide of how to procure against UK contracts here.


Procuring in Agresso vs manually (UK procurement only)

View a step-by-step guide on how to procure in Agresso and how to procure manually in the UK here.

The selection of the procurement process will be based on different criteria, such as estimated costs, risks and the lead time available.


Procurement through partners

The financial thresholds detailed here only apply to programmes following British Red Cross or IFRC procurement guidelines. Financial thresholds for each NS will have to be defined and agreed locally, and individual donors can define different thresholds and processes. The GAD determines which guidelines will have to be followed.

View and download the procurement process for UK international here.


Using the Movement’s resources

The British Red Cross has access to ICRCestablished procurement contracts. They are a preferred option when procuring NFIs, as they are subjected to strict QA testing from the ICRC internal QA team and from third-party service providers mandated to verify the quality of the items manufactured by the supplier. Procurement through an ICRC contract must be managed by UK logistics.

Using ICRC contracts for procurement:

View and download a diagram explaining how to use ICRC contracts for procurement here.


British Red Cross can also access IFRC-established contracts. They are particularly useful in the replenishment of pre-positioned stocks, with delivery at the IFRC warehouses (regional logistic units). A global logistics services agreement governs the relationship between the British Red Cross and the IFRC as a procurement service provider. Procurement through an IFRC contract must be managed by British Red Cross UK logistics.

View and download a diagram explaining how to use IFRC contracts for procurement here.

Quote-based procurement

Depending on organisational policies, some purchases will require one or more quotes to be obtained from suppliers (see British Red Cross/IFRC thresholds table).

The requestor will complete and have their requisition form (in British Red Cross UK this is called the RFA) approved, indicating a desired timeline for delivery, before submitting the form to the designated procurement lead. The procurement lead will consult the market and inform the requestor on a realistic timeline for delivery of the requested items (they can refer to the procurement plan for this).

Depending on the complexity of specifications, an RFQ form or RFQ document should be shared with suppliers for purchases, in order to ensure that all potential bidders receive the same information about the requested goods or services. RFQs should be shared with known suppliers and do not need to be advertised or published. They should clearly state the criteria against which the bidders will be evaluated, which must be agreed with the requestor. RFQs can be shared as simple forms to fill out, or as a formal, more detailed document.

When multiple quotes are received, they are evaluated against each other in a CBA that captures the selection criteria, calculates a weighted score per supplier and gives recommendations as to which is the most suitable supplier. The CBA must be prepared by the procurement lead and submitted to the Committee on Contract (CoC) if one is appointed and otherwise to the logistics team lead, the finance team lead and the budget holder for approval. Where relevant and specified in the original request, technical expertise can be sought (and the technical expert must also sign the CBA).

As part of the analysis, supplier due diligence must be carried out (financial and credit check, sanctions check, counter-terrorism check, ethical policies and standards check, etc.). Note that in the case of FSP and voucher vendors, financial and credit checks can be particularly challenging: pay special attention to the nature of documents required as part of submissions, to avoid failed tenders. For more details on procurement for cash transfer programmes, go to the Procurement to support cash programme delivery section of Procurement of Special Items and Services).

As part of the selection process, it is good practice to request that bidders submit samples of the goods or services they will supply to the procurement lead. Samples should be anonymised by the logistics team and shared with the requestors for their input.

Best and final offers text box

After the quotes’ analysis, a purchase order or contract must be drafted and submitted for approval, together with the complete file (including approved CBA, approved waiver (if applicable) and recommendations).

In UKO, this means raising the purchase order in Agresso and submitting for approval.


View a step-by-step guide of what to do when multiple quotes are needed here.


Tendering for goods or services

Tendering as a British Red Cross partner

As part of the development of a procurement policy, every organisation should define a requisition value above which the market will have to be consulted in more details, via a Request for Proposal (RFP). It is important that the procurement lead works closely together with the requestor to make sure all details are captured in the RFP.

The total requisition value is not the only criterion defining the need for a tender – some levels of risk identified will drive the decision to tender for specific services even below the agree tender threshold (see the Risk Management – Identifying Risks section of Definitions and Concepts).

RFP – details

  • Production requirements – to help bidders structure their offer.
  • Submission instructions – ways to submit, deadline.
  • Terms and conditions of purchase.
  • Bidder response document – standard format for all bidders to use to detail their offer.
  • Bid evaluation criteria and schedule – include timings and location details for events such as bid opening ceremony.
  • Declaration of undertaking – optional IFRC addendum procurement guidelines – mandatory if conducting a tender under IFRC rules.

The RFP must be published for a minimum of two calendar weeks for local tenders and three weeks for international tenders. It is usually better to have tenders for cash transfer programming advertised for a minimum of three weeks.

Up to an agreed threshold, it has to be shared with known suppliers only, in a closed tender. Known suppliers can be listed on a database or can be added to the database before sharing the RFP through an Expression of Interest (EOI).

Above that threshold, the RFP will have to be advertised publicly on an online platform or in local newspaper; all interested parties can submit a proposal. In open tenders, reaching out to specific suppliers to signpost them to the public announcement is authorised, to encourage them to bid for the tender.

Restricted tender occurs when only pre-qualified operators can submit offers. Restricted tenders generally start with calls for EOIs, which allows for the advanced selection or shortlisting of suppliers that are then asked to respond to the tender. Restricted tenders are used when the legal framework of procurement is stricter than usual, for example in the procurement of pharmaceutical products, vehicles, or financial services, where suppliers must adhere to certain standards.

  • Open tender
    – Any bidder can submit an offer against the RFP.
    – No pre-vetting of suppliers.
  • Closed tender
    – Only registered supplier must be consulted
    – Registration of new suppliers done through EOI before sending out RFP
  • Restricted tender
    – Only pre-qualified suppliers can submit an odder against the RFP.
    – Pre-qualification is done through EOI.
    – Pre-qualified suppliers are added to a supplier database.

Bids can be submitted physically or electronically (in UKO, they can only be submitted electronically through an e-procurement system, accessed by CPT or international logistics). All bids received must be recorded on a bid opening minutes format, and confirmation of receipt must be sent to each bidder within 24 hours of the deadline stated in the RFP.

Where bids have been submitted electronically but outside of the e-procurement system, they should be sent to a generic email address that only one person can access (British Red Cross international logistics use BRC_International_Logistics@redcross.org.uk).

If bids are received in hard copies (physical copies), it is good practice to use a Bid submission register. After opening the bids, they can be evaluated by:

  • a designated group of stakeholders
  • a CoC (a minimum of two people, appointed by CPT or by the procurement lead – this is helpful where technical and programmatic considerations need to be considered for the technical evaluation)
  • the procurement lead, where no CoC or stakeholder group has been appointed.
A textbox describes the role of the Committee on Contract which must be appointed for any tender unless the requirement is waives

Bids must be shortlisted (remove any bids that are obviously unacceptable), scored against the set criteria in a CBA and due diligence, including sanctions and counter-terrorism checks, must be completed (see guidance).



The CBA must be approved by requestor, budget holder, finance approver, logistics approver and where needed by a technical expert, or by the tender committee (or CoC).

The successful bidder must be informed via an award letter that references the tender number, terms and conditions and policies that the supplier must agree to. The award letter should invite the successful supplier for contract negotiations and signature.

View and download a diagram of the process following CBA approval here.

Unsuccessful bidders must be informed through standard letters of regret once the contract with the successful bidder has been confirmed – informing them before then puts the organisation at risk in case the contract cannot eventually be awarded to the successful bidder.

Joint tendering – Tenders can be run in collaboration with other RCRC members. This requires significant coordination in the absence of a standard approach. There are ongoing initiatives to coordinate and streamline the process. Contact the logistics coordinators for overseas joint procurement, and the SLM for UK-initiated procurement.


Running a tender from UKO – specifics

A diagram shows the process of running a tender from the UK office of the British Red Cross

Read more about running a tender from UKO here.


Supplier due diligence – counter terrorism and sanctions checks

A carefully designed due diligence framework helps organisations strengthen risk management by establishing healthy partnerships and mitigating criminal, contractual or reputational risks.

Due diligence should rely on a mix of self-certification provided by prospective partners and independent research.

Counter terrorism and sanctions check are part of the supplier due diligence process.

Whenever the international directorate at the British Red Cross or its partners consider engaging with a supplier through a procurement process with a total estimated spend above £5,000 and using British Red Cross funds, the prospective suppliers should be checked using the MK Denial website before being issued a purchase order or contract.

This threshold can be set lower than £5,000 in cases where additional donor requirements apply or in cases where the risks are higher – for example, due to the context or nature of items purchased. The agreed threshold must be proposed as part of the risk register developed as part of the IQM process, agreed with the partner and stated in the GAD. The threshold agreed in the GAD supersedes the standard £5,000 threshold.

If a supplier is issued with multiple POs with an estimated total value above £5,000, it is recommended that a framework agreement (FWA) is established following a tender process. Where the procurement lead organisation has a framework agreement or long-term agreement (LTA) in place with a supplier, the supplier should be checked periodically, as per the agreed review schedule (this would usually be annual). The supplier due diligence guidance note explains how and when to perform counter-terrorism checks.


Contracting/raising purchase orders

When procuring as a British Red Cross partner

Following the selection process and due diligence checks, POs or contracts formalise the agreement with the selected supplier.

The following must be included in the purchase orders and contracts:

  • original requisition number
  • tender reference number
  • details of items ordered: standards, quantity, unit price
  • added fees, taxes, delivery costs
  • payment terms
  • for international procurement: applicable incoterm.

The following must be included in contracts:

  • delivery schedule and payments
  • service level agreement
  • all relevant policies attached.

Service level agreement includes provisions for claims and penalties.

It is good practice to include penalty clauses in contracts. Penalty clauses should be linked to the service level agreement and address all points agreed in it: quality, lead times, and all agreed terms and conditions (such as packaging instructions, documentation required, etc.).


Purchase ordersContracts
Raised byProcurementProcurement
ConsultedLegal
Approved by*Budget holder
Finance
Procurement
Budget holder
Finance
Legal

*Seniority of the signatory of the PO or contract is determined by the total procurement value or is the authorised legal representative of the organisation

A set of template contracts is available for download at the end of the section.

  • transport contract
  • consultancy contract
  • rental contract (lease agreements – see template for warehouse lease contract)
  • framework agreement
  • financial services provider contract template (ICRC template, please adapt and contact British Red Cross international logistics team for support).

Contract amendments:

Contract changes: must be documented, approved by the original approver of the contract, dated and kept on file with the original contract.

Contract extensions: at the expiry date of a contract or when the total value of it has been spent, a contract extension form must be filled out to request an extension. The contract extension form must be signed off by the head of procurement (in BRC, this is the head of CPT or the head of international logistics).

A contract can only be renewed once, and the duration of the extension cannot exceed the duration or value of the original contract. At the expiry date of the extended contract, a full procurement process must be completed again (or waived through a waiver request).


Contracting/raising purchase orders – UK specifics

The requirements in the Contracting/raising purchase orders as a British Red Cross partner section apply, and the CPT must be informed ahead of contracting. British Red Cross corporate procurement tools must be used, i.e. a requisition must be raised in Agresso and approved as per the approval matrix designed in Agresso; once it has been approved, a purchase order or contract can be raised.

Contract amendments for UK contracts: request must be submitted to CPT, who will draft a contract amendment, sign it and share with logistics.


Framework agreements

In general

Ideally based on the ‘80/20 procurement strategy’ so they cover the most procured items or highest spend lines, framework agreements (FWAs) are a specific type of contract that cover several purchases along a determined period.

FWAs should be used to source regularly procured and readily available products where the market prices are sufficiently stable, where the product specifications and prices are fixed for a period of time.

Standard items usually procured under framework agreements include:

  • printing material
  • office consumables and stationery
  • vehicle servicing and repairs
  • IT support
  • fuel
  • travel agency
  • generator service
  • standard and high-usage NFIs – blankets, tarpaulins, jerry cans, cook sets, etc
  • Financial services in cash transfer programmes (see the Procurement to support cash programme delivery section of Procurement of Special Items and Services).

A FWA is set up through a tender process (see the Tendering for goods or services section), by circulating a request for proposal (RFP) or expression of interest (EOI) to the open market. The FWA should be reviewed every one to three years.

Selection criteria must be similar to criteria in an RFP but can also include:

  • a minimum spend requirement
  • minimum order quantity or value requirement
  • a maximum spend allowance
  • fixed pricing for a standard list of items or fee (for example, travel agency that will apply a fee to each booking)
  • turnaround time, from order to delivery service-level agreement.

It is good practice to include penalty clauses in FWAs, just like in other contracts. Penalty clauses should be linked to the service level agreement and address all points agreed in it: quality, lead times, and all agreed terms and conditions (such as packaging instructions, documentation required, etc.).

Once set up with the framework agreement template, a purchase of any value can be made against the FWA, based on the approved price list or following the standard single quote procedure if no price list has been included in the FWA.


FWA set up in the UK for use in the UK

In the UK, the standard FWA awarded by CPT is a two-year contract, with the possibility of a one-year extension (this can change and must be agreed at the start of the project). To set up a FWA, the same steps are followed as for a tender, with the supplier management details added to the specifications. CPT will support by setting up supplier review meetings as needed.


Purchasing

Purchasing is the process of buying items or services without a full procurement process. It can be done in various ways in the British Red Cross.

Purchasing options

From framework agreement (FWA)

  • There is no need to complete a procurement process.
  • Purchase order can be raised against the FWA directly, per the agreed unit prices or following a quick-quote process.

With a procurement card

  • Procurement card can be requested from SSC.
  • The card can be used as a credit card for small purchases under £1,000.
  • Maximum credit amount is £5,000.

With a Caxton card

  • Caxton card can be requested from SSC.
  • For use for personal expenses while travelling.
  • Not for operational expenditure unless on an ERU deployment.

Online purchasing

  • Out-of-pocket up to £1,000.
  • > £1,000: must be managed by CPT procurement lead.

Petty cash

  • Out-of-pocket or with professional cash advance up to £1,000.
  • Claim expenses/reconcile advance against receipts.

Read the next section on Managing procurement here.



Download the full section here.

When working on a project, make sure the workload that procurement represents is clearly identified so it can be absorbed by your team. The standard roles involved in procurement are as below (see the IFRC logistics competency framework for reference):


A diagram depicts the three tiers to making a procurement plan. Tier 1 - strategic, the logistics coordinator develops the  plan. Tier 2 - tactical, the procurement manager implements the plan. Tier 3 operational, the procurement officer and purchaser source goods, monitor the market and report on procurement

Available to download here.


Standard job descriptions for procurement-focused positions can be requested from the international logistics team.


The logistics team’s structure should be defined in the early stages of the implementation phase, as per the IQM process. Based on the project plan and other planning tools, such as the procurement plan and budget, a resource plan should be defined and implemented to support the programme’s activities.


At that stage, the programme team should define:

  • the need for UK-based logistics support – some procurement processes will require support from the UKO-based logistics team
  • the need for in-country logistics support.

In terms of cost of procurement: the cost of items and services to be procured will often be budgeted while other costs related to procurement may be overlooked, such as delivery, administrative or handling costs. The identified procurement lead should make sure that these costs are budgeted for.


Read the next section on Procurement processes in the British Red Cross here.



Download the full section here.


As part of the implementation phase* of the project, where the design phase* has helped identify needs that cannot be fulfilled with British Red Cross-owned resources (such as stock, staff, licenses or premises), the programme team and procurement lead will need to raise a procurement plan. This will capture sourcing options and manage the programme team’s expectations in terms of what should be available and when and enable the fulfilment of the activities that the programme has defined for itself.

The procurement plan is as much a work plan for the procurement team as a communications tool, and it will act as a service-level agreement between the procurement team/lead and the programme team/lead.

* These refer to the different stages identified in the British Red Cross International Quality Methodology (IQM) process. Details available from British Red Cross staff if required.


The procurement plan

How a procurement plan is designed


A diagram depicts how a procurement plan is designed. The steps are: programme-defined objectives, programme-scheduled activities, goods and services needed, procurement support needed, procurement process definition, procurement plan

An indicator of likelihood of change should be included in the programme plan for each activity and objective.


Roles and responsibilities in developing a procurement plan


ResponsibleProcurement lead | Programme team
AccountableLogistics department
ConsultedFinance | Warehouse | Technical adviser I UKO logs
InformedProgramme quality management | Programme team

Available to download here.


Who can help develop a procurement plan?

  • UKO logistics
  • for cash programmes: the Cash Hub
  • experienced programme managers
  • supply chain experts with local expertise
  • finance staff (for cost indications)
  • IFRC, ICRC, HNS colleagues and other organisations.

What to consider when developing the procurement plan

How to obtain the goods

There are different methods to ensure that the material needed for the delivery of a programme are made available to the programme team.

  • procurement – for high-value or high-risk items needed
  • purchasing – for lower value, low-risk items needed
  • donations – where reliable sources have resources beyond their needs
  • loans – where items can be temporarily supplied by partners with subsequent replacements.

Waivers must be submitted to the UKO head of logistics and approved on an individual basis, regardless of the value of the procurement. For procurement conducted in UKO, this is the role of the CPT but UKO logistics can always advise and inform.

All waivers requested and obtained must be logged on the procurement plan. For UK-based procurement, a list of the waivers requested/obtained must be kept on a list of exceptions.


Where to obtain the goods from and where to deliver them

  • local – small-scale retail, loan or donation system
  • national – large suppliers who are part of a national supply network, national partners
  • international – international supplier or donors, IFRC, ICRC and PNS.

Note: the procurement plan also needs to define the exact delivery point for all the goods or services to procure.


Defining responsibilities

The below table displays an example of how the procurement process can be broken down into steps, matching each step with responsible, accountable, consulted and informed stakeholders.

This matrix should be completed, formally or informally, for each large procurement that is undertaken. There can be as many steps added to the matrix as necessary!

ResponsibleAccountableConsultedInformed
Defining needs
Raising requisition(s)
Validating procurement
process/route
Procurement sign-off
Contract negotiation
Order management
Quality check at delivery

Available to download here.


When to conduct procurement

  • Link to project timeline – match up procurement timeline to project objectives. Identify dependencies between activities.
  • Procurement lead time – sourcing, contracting, manufacturing delivery – how long will it take?
  • Reverse logistics plan – plan for any returns or exchanges which could be required.

Documents to support the procurement plan development


Reference documents for procurement plan development:

  • project plan
  • financial approvals matrix
  • project budget
  • specialist procurement guidelines*
  • donor requirements*
  • local procurement legal framework
  • due diligence reports*
  • audit reports*
  • market assessment*
  • HR matrix and organogram.

* Not always available or relevant


The scope of the required a market assessment (how deep and how wide does it need to be?) needs to be identified at the idea stage of the project (see British Red Cross IQM guidance document) in alignment with both the available time and resources and the objectives defined for the project.

There are several tools available in the International Red Cross and Red Crescent Movement to support logisticians and programme teams in the market assessment and analysis process:

  • Market analysis survey tool to capture average prices and availability of standard goods and services.
  • Market assessments for cash-based interventions (such as RAM or MAG) are key to understanding the functionality of markets, and its ability to support the objectives of the programme. They are available from the Cash Hub. The output of the market analysis will feed into the response options analysis and programme design and decision making.

For more details on market assessment and monitoring for cash programmes, refer to the Cash Hub and the logistics support to cash programmes RACI matrix, from the Market Assessment and Analysis Principles paper.


Validating a procurement strategy

Based on the procurement plan and the estimated costs of items or services to be procured, it is helpful to identify the procurement lines that will consume the biggest share of the total cost at the design phase. This is useful for understanding where the efforts to conduct procurement should be focused.

A good rule of thumb to use is pareto analysis: calculate the total estimated spend on procurement, identify the 20 per cent highest-value procurement lines and invest 80 per cent.

There are other considerations to take into account, such as the urgency of the requirements. However, based on the pareto analysis, it will be critical to define and plan the procurement process of those lines which make up more than 80 per cent of the expected spend.

The pareto analysis can be based on expected amount to be spent, or on expected quantities to be procured. Typically, items that are purchased more than 50 per cent more often than others (and at regular intervals) should be purchased through long-term procurement agreements such as framework agreements.

In the UK, this is the role of the CPT at SSC – the UK logistics team act as an adviser or stakeholder in the procurement planning and strategy, driven by similar analyses. See the pareto step-by-step tool for more details on how to build your own pareto analysis into your procurement strategy.

The procurement strategy will flow from the procurement plan and from the pareto analysis and evolves based on the procurement reports that are available throughout the lifecycle of a project.

View and download a diagram of the procurement strategy flow here.


Read the next section on Planning resources for procurement here.



Download the full section here.


Procurement vs purchasing

The terms “procurement” and “purchasing” are often used interchangeably but purchasing is just one of the many activities involved in procurement.  

Procurement is concerned with acquiring the goods, services and work that are vital to an organisation. Procurement encompasses both sourcing and purchasing. 

Sourcing is a set of activities conducted before purchasing, usually including market research

It revolves around the needs definitions and formalisation of the relationship with potential providers of required goods and services.  

A diagram depicts activities involved in sourcing such as supplier identification, supplier management, contract negotiation and category analysis

Purchasing focuses on how goods and services are ordered and delivered.  

At the time of purchasing, sourcing has usually either already been completed, or its requirement may have been waived under exceptional circumstances. 

A diagram depicts the activities involved in purchasing, such as identifying needs, making a purchase order, receiving a goods service order and sending an invoice

Roles and responsibilities

Roles and responsibilities evolve along the procurement cycle. 

RACI matrices are used throughout this manual. They break a process into steps, specifying who is responsible, accountable, consulted and informed at each step of the process.


Sourcing RACI matrix

SOURCINGResponsibleAccountableConsultedInformed
Needs definitionRequestorRequestorTechnical adviserProcurement lead
Category analysisProcurement leadProcurement managerTechnical adviserRequestor
Supplier identificationProcurement leadProcurement managerTechnical adviserRequestor
Request for quotesProcurement leadProcurement managerRequestorRequestor
Contract negotiationProcurement leadProcurement managerLegal | Finance
Requestor
Requestor
Contract managementProcurement leadProcurement managerLegalRequestor
Supplier managementProcurement leadProcurement managerTechnical adviser
Requestor
Requestor
Risk managementProcurement leadProcurement &
supply chain dept.
Legal | Finance
Requestor
Requestor
Finance

Available to download here.


Purchasing RACI matrix

PURCHASINGResponsibleAccountableConsultedInformed
Needs definitionRequestorRequestorTechnical adviserProcurement lead
Raise requisitionRequestorRequestorTechnical adviserProcurement lead
Obtain internal
approvals
RequestorRequestorBudget holder | FinanceTechnical adviser
Raise purchase
order(s)
Procurement leadProcurement &
supply chain dept.
Budget holder | Finance
Requestor
Requestor
Goods receptionWarehouse
Proc. lead | Requestor
Procurement &
supply chain dept.
Technical adviserRequestor
PaymentFinance leadFinance dept.Procurement &
supply chain dept.
Requestor

Available to download here.


Authority to procure

Authority to conduct procurement includes entering contracts, negotiating them or amending them and inviting suppliers to bid for contracts for the organisation.

Authority to procure is usually, but not exclusively, held by the logistics division.

The Grant Agreement Document (GAD) that the British Red Cross signs with the PNS, HNS or IFRC may also delegate procurement authority, by which the British Red Cross allows partners to conduct procurement activities with funds that it provides to them.

A text box describes what Authority to procure means: The person with procurement authority is accountable for improper use of this authority or for anyone acting without proper authority in their delegation, office or programme

Authority to procure must be stated in job descriptions for roles which include procurement responsibilities.

The programme manager can propose a list of staff who should be given authority to procure.

In all cases, the regional logistics coordinator at the British Red Cross should be consulted by the programme manager when allocating authority to procure.

It is good practice to keep records of authority to procure – staff with authority to procure should fill out a Delegation of procurement authority, to be signed off by the head of logistics and head of programme as applicable.

When the British Red Cross signs an integration agreement with the IFRC in a country where the British Red Cross works with the NS (in other words, a multilateral partnership), the integration agreement sometimes includes procurement rules. In this case, the IFRC’s procurement procedures apply to British Red Cross-led procurement. This is also the case when NS staff conduct procurement under a British Red Cross-funded programme.

Where the IFRC is not part of the partnership, the applicable procurement thresholds will be defined in the GAD with the PNS (this is called a bilateral partnership).


Procurement principles

Principles of organisation:

  • placing the requirements of the British Red Cross at the heart of what we do
  • managing our suppliers in a way that mitigates the exposure to any risk
  • driving value for money
  • enabling effective competition that is open, fair and transparent
  • driving continuous improvement that delivers innovative solutions and sustainable benefits.

General procurement principles:

  • proportionality – the larger the risk, the more complex the process
  • fairness – all suppliers are treated equally
  • transparency – all suppliers receive the same information
  • value for money – the best possible quality at the best possible price, for the best possible impact
  • segregation of duty – different decision-makers along the process
  • respect for applicable framework.

Risk management

Identifying risks

All procurement activities present different levels of risk to the organisation conducting them.

Before starting the procurement process, it is important to assess that risk and the appetite there is to expose the organisation to it.

Adopt a risk-based approach that considers different types of risk and the appropriate mitigating actions to adhere to the general and organisational procurement principles.

There are different types of risks in procurement:


Procurement risks:

Financial

  • relates to the total value of the procurement
  • particularly high in cash transfer programmes where the total value of transfers may have to be paid in advance

Type of goods

  • some goods are “riskier” than others to procure

Supply chain

  • actors involved in the supply chain, transport needs, etc.

Payment recipient

  • investigation into ownership of engaged companies may be required

Country of origin/destination

  • legal framework for manufacturing, shipping or quality management may be below acceptable levels

Programmatic risks

  • regardless of value, a specific procurement being delayed or compromised can put the entire programme at risk.

Managing the identified risks

Use a risk management matrix and discuss options to mitigate risks with the procurement lead.

Use a risk assessment tool to capture these factors and include the findings in a programme risk register.

Remember
Risk Rating = Likelihood x Impact


The risk management matrix measures the likelihood of risk against the impact of an action

Available to download here.

Possible outcomes of the risk analysis are:

  • The level of risk is acceptable to conduct the procurement.
  • The procurement process needs to be flagged on a risk register for the consideration of management.
  • The procurement process should be cancelled.

The decision must be made by the programme manager, in consultation with the procurement and finance teams.


Due diligence

Due diligence involves taking steps to be certain that the relationship with the supplier does not put the organisation at risk. This is done through a comprehensive appraisal of a supplier that looks at assets, liabilities and processes against financial, ethical and environmental considerations.

When due diligence is considered as part of a procurement process, it is the responsibility of the procurement lead to conduct it. The due diligence framework in the British Red Cross is managed by the corporate procurement team (CPT), and the international department supports the implementation of systems to ensure that due diligence is conducted appropriately.


Fraud and corruption

An anti-fraud and corruption policy should be in place in each partner organisation that is involved in procurement activities. The British Red Cross anti-fraud and corruption policy sets out our approach to preventing fraud and corruption within the organisation, as well as how to manage it if it occurs. It is available from RedRoom or from the logistics team for reference.


Conflict of interest and confidentiality agreements

Conflict of interest is a form of corruption and occurs when someone conducting a procurement process has an interest in driving it in a specific direction, based on relationships, financial interests or favouritism.

Anyone involved in procurement should be aware of emerging conflicts of interest and make them explicit. They must also declare any way in which they might have a conflict of interest in a particular procurement process, through a declaration of conflict of interest form (see conflict of interest policy).

All instances of failure to disclose a conflict of interest will be investigated in line with the established disciplinary process, which may lead to dismissal where gross misconduct is proved.

For details on Due diligence and counter-terrorism checks, go to the Supplier due diligence section of Sourcing for procurement.


Read the next section on Planning procurement here.



Download the full section here.

Procurement



Definitions and concepts

The principles that drive procurement activities.

Learn more in the Definitions and concepts section.


Risk management

How to manage risk in procurement activities.

Learn more in the Risk management section.


When to procure

How to plan for effective procurement, monitor progress, evaluate and report on procurement.

Learn more in the Planning procurement section.


Why to procure

When required goods or services are unavailable to the organisation internally, they need to be sourced from third parties.

Learn more in the Sourcing for procurement section.


What to procure

How to select the best possible supplies to procure, delivering quality and value for money. How to procure items with special requirements.

Learn more in the Procurement of special items and services section.


How to procure

Procurement processes and procedures used at the British Red Cross and procurement resources within the Red Cross Movement, and how to use them.

Learn more in the Planning resources, Procurement processes, Sourcing and Managing procurement sections.


Who should procure

The stakeholders involved in procurement processes, roles and responsibilities.

Learn more in the Definitions and concepts and Planning resources for procurement sections.


Download the whole Procurement chapter here.